What inspection work does the gas boiler have to do during the test run?

2019 / Jun / Mon
During the trial operation phase of the condensing gas hot water boiler, FANGKUAI Boiler manufacturers strongly recommend that you carry out the following inspections:

1. Make sure there is no liquid or flammable material next to the boiler.
2. Ensure that the circuit is connected correctly and the ground wire is well connected to the grounding system.
3. Turn on the gas switch and check if the connection is stable, including the burner.
4. Ensure that the boiler setting is suitable for the gas type
5. Check if the flue gas pipe is properly installed and unobstructed.
6. Make sure all shutoff valves are open.
7. Make sure the system is filled with water and completely drained.
8. Check if the circulation pump is turned on.
9. Purify the system by venting the air in the gas pipeline through the pressure discharge valve of the gas valve port.
10.The installer must provide the boiler operation instructions to the user and forward the installation manual to the user.